Background (Updated October 2006)
Springbank Dam
was constructed in 1929 to create a local water supply reservoir and provide
recreational opportunities. Traditionally, Springbank Dam holds back water for six
months each year from approximately May 24th until early November. The
reservoir is a popular setting for a variety of passive and active
recreational uses, including canoeing, fishing, cycling and walking.
Springbank Dam
is owned by the City of London and is operated by the Upper Thames River
Conservation Authority (UTRCA) for recreation, flood protection, and
fisheries management.
The purpose of
the Springbank Dam Rehabilitation is to ensure the safe operation of
Springbank Dam. Studies in 2000 and 2002 recommended that the dam be
rehabilitated to meet provincial dam safety requirements. The rehabilitation
project includes repairing erosion protection that was damaged in the
flood of
July 9, 2000 Thames River flood, replacing failing stop logs with gates
that will be less prone to blockage by debris, and repairing other aspects
of the dam such as the concrete.
Top
Priorities for the Rehabilitation Project
Improved
Public Safety
Safety of people and property remain the priority of the UTRCA. The Springbank Dam structure is
in poor condition and requires upgrading and repair to ensure that it does
not compromise the UTRCA flood control system. Various public safety
upgrades are also proposed as part of the project.
Environmental Health
The UTRCA promotes a healthy environment and wishes to ensure that
the project proceeds in a manner that does not, in any way, degrade the
health of the ecosystem.
Stakeholder Participation
The rehabilitation of Springbank Dam is an inclusive project.
Various stakeholders have been involved in the project through the EA
process (see the EA
report for lists of organizations visited and comments received) and through stakeholder participation in the Science and Engineering
Technical Committee initiated by the City of London.
Project
Timeline
-
July 2007: Construction at Springbank
resumes. Project scheduled to be completed in fall '07.
-
April, May and June 2007: As required by MNR,
all construction activities in river ceased to allow for spring fish
migration.
-
February 2007: City of London issued a
press release indicating
that, due to weather-related delays, construction will not be complete
in time to allow filling of the Springbank Reservoir for the normal 2007
summer season.
-
Fall 2006: Construction progress slowed by
high water levels. The Thames River average flow at Byron over the month
of October 2006 was the highest ever recorded in October (since records
began in 1922). The November 2006 average flow was the fifth highest
November on record, and December 2006 average flow was the second
highest December on record.
-
September 2006: Construction started on the rehabilitation of
Springbank Dam. A
construction tender was awarded by the City of London in August 2006 to
MacLean Taylor Construction Ltd. of St. Marys, Ontario. Hatch Acres of
Niagara Falls are the Consulting Engineers overseeing the construction.
(See the September 25, 2006
Media Release and Frequently Asked Questions)
-
August 2006: Updating of Agency approvals,
Tender approval by the City of London.
-
June 2006: Tender release by the City of
London.
-
April to June 2006: Fish Passage Baseline Studies undertaken by
Biotactic. Study supported by City of London, Upper Thames River
Conservation Authority, Ministry of Natural Resources, Fisheries and
Oceans Canada.
- October 2005: The rehabilitation of Springbank Dam, which was
set to begin on October 1, 2005, has been postponed due to developments
including but not limited to:
-
delay in the issuance of work permits,
-
need to assemble more baseline data for
fisheries assessment,
-
dramatic increase in the project costs due to
recent developments.
The intention is to implement this project in 2006.
Options for next year are being studied by the City of London and the
engineering consultant. The City of London is reviewing the project
budget, which may rise significantly due to postponement. The City is
currently seeking additional funding from Provincial and Federal
partners who were originally sharing the costs in 1/3 portions. The
UTRCA is pleased that the City of London has gained an extension to the
project's timeline as it will allow more time to assess the fish
movement at Springbank Dam.
-
September 2005: Fish Passage Monitoring
Framework completed by Ministry of Natural Resources with input from
SETC.
-
November 2004 and continuing: SETC
information-sharing leads to discussion on fish passage at existing dam
and for proposed gate rehabilitation project at dam. Field
investigations by Committee members are initiated to inventory species
and distribution.
-
October 29,
2004: Science and Engineering Technical Committee (SETC) initiated by the City
of London, chaired by the Ministry of Natural Resources, to investigate
issues raised about fish passage at the structure and potential for a
fishway.
-
August 3,
2004: UTRCA hosts stakeholder meeting regarding fish ladder issue at
Byron Public Library.
-
January
2004: Environmental assessment completed; public and agency review
period ended January 12, 2004.
-
October 22,
2003: Environmental assessment open house/public meeting held at Byron
Public Library, London.
-
August 2003:
Project description report and class environmental assessment report
completed.
-
2002:
City of London received funding to rehabilitate the dam and repair the
failed erosion protection through the Ontario Sports, Culture and
Tourism Program and the Canada-Ontario Infrastructure Program.
-
May 2, 2002:
Dam Safety Assessment completed by Acres International (now
Hatch-Acres). Report identified the need for better debris passage,
improved operational efficiency, and repairs to the portions of the dam
damaged in 2000.
-
July 9,
2000: Overtopping of the dam due to debris accumulation during a flood
damaged the south bank and raised concerns about the safety of the
structure.
For More Information
,
Marketing Specialist, Upper Thames River
Conservation Authority
tel.: 519-451-2800
ext. 275, fax: 519-451-1188
or
,Supervisor,
Water Control Structures, Upper Thames River
Conservation Authority
tel.: 519-451-2800
ext. 244, fax: 519-451-1188
|